[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258891":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1258891,842,2,"多选题","在双代号网络计划中，某项工作的最早完成时间是指其（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","开始节点的最早时间与工作总时差之和",false,{"key":16,"text":17,"correct":18},"B","开始节点的最早时间与工作持续时间之和",true,{"key":20,"text":21,"correct":14},"C","完成节点的最迟时间与工作持续时间之差",{"key":23,"text":24,"correct":18},"D","完成节点的最迟时间与工作总时差之差",{"key":26,"text":27,"correct":14},"E","完成节点的最迟时间与工作自由时差之差","BD","双代号网络计划中，某项工作的最早完成时间是指其开始节点的最早时间与工作持续时间之和和完成节点的最迟时间与工作总时差之差。",{"id":6,"name":31,"category":32,"favorite":33},"(土建施工)专业管理实务 岗位知识","建筑工程",0]