[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258890":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1258890,842,2,"多选题","施工进度计划的审核内容包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","施工进度计划是否符合承包合同中的工期要求",true,{"key":16,"text":17,"correct":14},"B","施工进度计划中的内容是否有遗漏，分期施工是否满足分批交工的需要和配套交工的要求",{"key":19,"text":20,"correct":21},"C","施工顺序安排是否符合施工程序的要求",false,{"key":23,"text":24,"correct":14},"D","资源供应计划应满足施工进度计划的需要",{"key":26,"text":27,"correct":14},"E","施工图设计的进度是否满足施工进度计划要求","ABDE","施工进度计划审查应包括下列基本内容：（1）施工进度计划应符合施工合同中工期的约定；（2）施工进度计划中主要工程项目无遗漏，应满足分批投入试运、分批动用的需要，阶段性施工进度计划应满足总进度控制目标的要求；（3）施工顺序的安排应符合施工工艺要求；（4）施工人员、工程材料、施工机械等资源供应计划应满足施工进度计划的需要；（5）施工进度计划应符合建设单位提供的资金、施工图纸、施工场地、物资等施工条件。",{"id":6,"name":31,"category":32,"favorite":33},"(土建施工)专业管理实务 岗位知识","建筑工程",0]