[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258888":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1258888,842,2,"多选题","施工项目进度计划调整时，应考虑（ ）等限制条件，确保要求的进度目标得到实现。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","后续工作",true,{"key":16,"text":17,"correct":18},"B","项目经理部的管理力量",false,{"key":20,"text":21,"correct":14},"C","总工期",{"key":23,"text":24,"correct":18},"D","已完工作",{"key":26,"text":27,"correct":18},"E","安全管理要求","AC","施工项目进度计划调整时，应考虑后续工作和总工期等限制条件，确保要求的进度目标得到实现。",{"id":6,"name":31,"category":32,"favorite":33},"(土建施工)专业管理实务 岗位知识","建筑工程",0]