[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258886":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1258886,842,2,"多选题","编制建设工程施工总进度计划，主要用来确定如下哪几项工作（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","各单项工程或单位工程的工期定额",false,{"key":16,"text":17,"correct":14},"B","建设的要求工期和计算工期",{"key":19,"text":20,"correct":21},"C","各单项工程或工程的施工期限",true,{"key":23,"text":24,"correct":14},"D","各单项工程或单位工程的实物工程量",{"key":26,"text":27,"correct":21},"E","各单项工程或单位工程的相互搭接关系","CE","编制建设工程施工总进度计划，主要用来确定.各单项工程或工程的施工期限和各单项工程或单位工程的相互搭接关系。",{"id":6,"name":31,"category":32,"favorite":33},"(土建施工)专业管理实务 岗位知识","建筑工程",0]