[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258879":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1258879,842,2,"多选题","关于框架结构工程钢筋混凝土预制桩沉桩顺序的说法，正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","当基坑不大时，打桩应逐排打设或从中间分头向四周或两边进行",true,{"key":16,"text":17,"correct":14},"B","对于密集桩群，从中间分头向四周或两边对称打设",{"key":19,"text":20,"correct":21},"C","当一侧毗邻建筑物时，由另一方向向毗邻建筑物施打",false,{"key":23,"text":24,"correct":14},"D","当基坑较大时，宜将基坑分为数段，然后在各段范围内分别施打",{"key":26,"text":27,"correct":21},"E","对于基础标高不一的桩，宜先浅后深","ABD","框架结构工程钢筋混凝土预制桩沉桩顺序当基坑不大时，打桩应逐排打设或从中间分头向四周或两边进行，对于密集桩群，从中间分头向四周或两边对称打设，当基坑较大时，宜将基坑分为数段，然后在各段范围内分别施打。",{"id":6,"name":31,"category":32,"favorite":33},"(土建施工)专业管理实务 岗位知识","建筑工程",0]