[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258878":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1258878,842,2,"多选题","确定施工顺序的基本要求包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","必须符合施工工艺的要求",true,{"key":16,"text":17,"correct":14},"B","必须与施工方法协调一致",{"key":19,"text":20,"correct":14},"C","必须考虑当地的气候条件",{"key":22,"text":23,"correct":14},"D","必须考虑安全施工的要求",{"key":25,"text":26,"correct":27},"E","必须考虑文明施工的要求",false,"ABCD","确定施工顺序的基本要求：①必须符合施工工艺的要求；②必须与施工方法协调一致；③必须考虑与施工组织的要求；④必须考虑施工质量的要求；⑤必须考虑当地的气候条件；⑥必须考虑安全施工的要求。",{"id":6,"name":31,"category":32,"favorite":33},"(土建施工)专业管理实务 岗位知识","建筑工程",0]