[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258874":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":27,"analysis":28},1258874,842,2,"多选题","深基坑施工中变形观测的内容有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","支护结构顶部的水平位移观测",true,{"key":16,"text":17,"correct":14},"B","临近建筑物的垂直位移、倾斜、裂缝观测",{"key":19,"text":20,"correct":14},"C","临近道路、地下管网设施的垂直位移、倾斜、裂缝观测",{"key":22,"text":23,"correct":14},"D","支护结构的垂直位移观测",{"key":25,"text":26,"correct":14},"E","支护结构倾斜观测","ABCDE","建筑工程施工变形监测：深基坑施工中变形观测的内容包括支护结构顶部的水平位移观测，支护结构的垂直位移观测，支护结构倾斜观测，临近建筑物、道路、地下管网设施的垂直位移、倾斜、裂缝观测。",{"id":6,"name":30,"category":31,"favorite":32},"(土建施工)专业管理实务 岗位知识","建筑工程",0]