[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258840":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1258840,842,2,"多选题","单位工程竣工成本分析的主要内容包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","竣工成本分析",true,{"key":16,"text":17,"correct":14},"B","主要资源节超对比分析",{"key":19,"text":20,"correct":21},"C","月（季）度成本分析",false,{"key":23,"text":24,"correct":14},"D","主要技术节约措施及经济效果分析",{"key":26,"text":27,"correct":21},"E","年度成本分析","ABD","单位工程竣工成本分析的主要内容包括竣工成本分析，主要资源节超对比分析和主要技术节约措施及经济效果分析。",{"id":6,"name":31,"category":32,"favorite":33},"(土建施工)专业管理实务 岗位知识","建筑工程",0]