[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258836":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1258836,842,2,"多选题","机械费用主要由台班数量和台班单价两方面决定，主要从（ ）方面控制台班费的有效支出。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","合理安排施工生产，加强设备租赁计划管理，减少因安排不当引起的设备闲置",true,{"key":16,"text":17,"correct":14},"B","加强机械设备的调度工作，尽量避免窝工，提高现场设备利用率",{"key":19,"text":20,"correct":14},"C","加强现场设备的维修保养，避免因不正当使用造成机械设备的停置",{"key":22,"text":23,"correct":14},"D","做好上机人员与辅助生产人员的协调与配合，提高机械台班产量",{"key":25,"text":26,"correct":27},"E","指定价格低廉的设备租赁单位，降低租赁费用",false,"ABCD","机械费用主要由台班数量和台班单价两方面决定，主要从以下几个方面控制台班费的有效支出：合理安排施工生产，加强设备租赁计划管理，减少因安排不当引起的设备闲置；加强机械设备的调度工作，尽量避免窝工，提高现场设备利用率；加强现场设备的维修保养，避免因不正当使用造成机械设备的停置；做好上机人员与辅助生产人员的协调与配合，提高机械台班产量。",{"id":6,"name":31,"category":32,"favorite":33},"(土建施工)专业管理实务 岗位知识","建筑工程",0]