[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258832":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1258832,842,2,"多选题","施工生产中计量控制的主要工作包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","投料计量",true,{"key":16,"text":17,"correct":14},"B","施工测量",{"key":19,"text":20,"correct":21},"C","施工机械设备数量计量",false,{"key":23,"text":24,"correct":14},"D","监测计量",{"key":26,"text":27,"correct":21},"E","施工人员数量计量","ABD","施工过程中的计量工作，包括施工生产时的投料计量、施工测量、监测计量以及对项目、产品或过程的测试、检验、分析计量等。",{"id":6,"name":31,"category":32,"favorite":33},"(土建施工)专业管理实务 岗位知识","建筑工程",0]