[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258810":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":27,"analysis":28},1258810,842,2,"多选题","造成施工进度计划偏差的影响因素包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","设计的变更",true,{"key":16,"text":17,"correct":14},"B","工期及相关计划的失误",{"key":19,"text":20,"correct":14},"C","工程条件的变化",{"key":22,"text":23,"correct":14},"D","管理过程中的失误",{"key":25,"text":26,"correct":14},"E","实施方案的修改","ABCDE","造成施工进度计划偏差的影响因素有：①工期及相关计划的失误；②工程条件的变化；③管理过程中的失误；④其他原因（工期的拖延、设计的变更、实施方案的修改）。",{"id":6,"name":30,"category":31,"favorite":32},"(土建施工)专业管理实务 岗位知识","建筑工程",0]