[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258808":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1258808,842,2,"多选题","建设工程无节奏流水施工的特点包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","各专业工作队不能在施工段上连续作业",false,{"key":16,"text":17,"correct":18},"B","各施工过程在各施工段的流水节拍不全相等",true,{"key":20,"text":21,"correct":18},"C","相邻专业工作队的流水步距不尽相等",{"key":23,"text":24,"correct":14},"D","专业工作队数小于施工过程数",{"key":26,"text":27,"correct":18},"E","有些施工段之间可能有空闲时间","BCE","建设工程无节奏流水施工的特点各施工过程在各施工段的流水节拍不全相等，相邻专业工作队的流水步距不尽相等，有些施工段之间可能有空闲时间。",{"id":6,"name":31,"category":32,"favorite":33},"(土建施工)专业管理实务 岗位知识","建筑工程",0]