[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258807":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1258807,842,2,"多选题","工程项目施工进度计划按编制对象可分为（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工总进度计划",true,{"key":16,"text":17,"correct":18},"B","控制性施工进度计划",false,{"key":20,"text":21,"correct":14},"C","单位工程施工进度计划",{"key":23,"text":24,"correct":14},"D","分部分项（专项）工程施工进度计划",{"key":26,"text":27,"correct":18},"E","实施性施工进度计划","ACD","工程项目施工进度计划按编制对象可分为：施工总进度计划、单位工程施工进度计划和分部分项（专项）工程施工进度计划；按计划的功能可分为：控制性施工进度计划、指导性施工进度计划和实施性施工进度计划。",{"id":6,"name":31,"category":32,"favorite":33},"(土建施工)专业管理实务 岗位知识","建筑工程",0]