[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258806":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1258806,842,2,"多选题","当工程施工的实际进度与计划进度不符时，需要对网络计划作出调整，调整的内容有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","调整关键线路的长度",true,{"key":16,"text":17,"correct":14},"B","调整非关键工作时差",{"key":19,"text":20,"correct":14},"C","增减工作项目",{"key":22,"text":23,"correct":24},"D","调整组织结构",false,{"key":26,"text":27,"correct":14},"E","调整资源的投人","ABCE","网络计划调整的内容包括：调整关键线路的长度；调整非关键工作时差；增、减工作项目；调整逻辑关系；重新估计某些工作的持续时间；对资源的投入作相应调整。",{"id":6,"name":31,"category":32,"favorite":33},"(土建施工)专业管理实务 岗位知识","建筑工程",0]