[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258799":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":27,"analysis":28},1258799,842,2,"多选题","控制性施工进度计划的作用主要包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","论证施工总进度计划",true,{"key":16,"text":17,"correct":14},"B","分解施工总进度计划",{"key":19,"text":20,"correct":14},"C","是编制实施性进度计划的依据",{"key":22,"text":23,"correct":14},"D","是施工进度动态控制的依据",{"key":25,"text":26,"correct":14},"E","是编制与该项目相关的其他各种进度计划的依据或参考","ABCDE","控制性施工进度计划的作用主要包括：①论证施工总进度计划；②分解施工总进度计划；③是编制实施性进度计划的依据；④是编制与该项目相关的其他各种进度计划的依据或参考；⑤是施工进度动态控制的依据。",{"id":6,"name":30,"category":31,"favorite":32},"(土建施工)专业管理实务 岗位知识","建筑工程",0]