[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258798":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1258798,842,2,"多选题","工程实际进度偏差影响到总工期时，可采用（ ）等方法调整进度计划。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","将顺序施工改为搭接施工",true,{"key":16,"text":17,"correct":14},"B","将部分任务转移",{"key":19,"text":20,"correct":14},"C","增加劳动力，提高劳动效率",{"key":22,"text":23,"correct":14},"D","增加资源投人",{"key":25,"text":26,"correct":27},"E","将平行作业改为顺序作业",false,"ABCD","工程实际进度偏差影响到总工期时，可采用将顺序施工改为搭接施工，将部分任务转移，增加劳动力，提高劳动效率和增加资源投人等方法调整进度计划。",{"id":6,"name":31,"category":32,"favorite":33},"(土建施工)专业管理实务 岗位知识","建筑工程",0]