[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258796":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1258796,842,2,"多选题","关于流水施工进度计划的描述，正确的有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","A按施工工艺顺序分施工过程、不分施工段绘制",false,{"key":16,"text":17,"correct":14},"B","B按施工组织顺序不分施工过程、分施工段绘制",{"key":19,"text":20,"correct":21},"C","C按施工顺序分施工过程、分施工段绘制",true,{"key":23,"text":24,"correct":21},"D","D各专业队在各施工段均应连续施工",{"key":26,"text":27,"correct":21},"E","E相邻专业队投人流水施工应实现最大搭接","CDE","流水施工进度计划按施工顺序分施工过程、分施工段绘制，各专业队在各施工段均应连续施工，相邻专业队投人流水施工应实现最大搭接",{"id":6,"name":31,"category":32,"favorite":33},"(土建施工)专业管理实务 岗位知识","建筑工程",0]