[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258777":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1258777,842,1,"单选题","在正常使用条件下，房屋建筑工程中供热与供冷系统的最低保修期限为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1个采暖期、供冷期",false,{"key":16,"text":17,"correct":18},"B","2个采暖期、供冷期",true,{"key":20,"text":21,"correct":14},"C","3个采暖期、供冷期",{"key":23,"text":24,"correct":14},"D","4个采暖期、供冷期","在正常使用条件下，房屋建筑工程中供热与供冷系统的最低保修期限为2个采暖期、供冷期。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]