[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258742":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1258742,842,1,"单选题","钢筋混凝土预制桩的强度须达到设计强度标准值的（）后方可起吊，如提前起吊，必须采取措施并经验算合格方可进行。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","A30%",false,{"key":16,"text":17,"correct":14},"B","B50%",{"key":19,"text":20,"correct":14},"C","C100%",{"key":22,"text":23,"correct":24},"D","D70%",true,"桩的起吊：桩的强度达到设计强度标准值的70%后方可起吊，如提前起吊，必须采取措施并经验算合格方可进行。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]