[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258709":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1258709,842,1,"单选题","专项方案如因设计、结构、外部环境等因素发生变化确需修改的，修改后的专项方案应当（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","可直接实施",false,{"key":16,"text":17,"correct":14},"B","经项目总工审批后实施",{"key":19,"text":20,"correct":21},"C","重新审核",true,{"key":23,"text":24,"correct":14},"D","经项目经理审批后实施","专项方案如因设计、结构、外部环境等因素发生变化确需修改的，修改后的专项方案应当重新审核。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]