[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258708":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1258708,842,1,"单选题","项目施工过程中，发生（ ）情况时，施工组织设计不需要进行修改或补充。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程设计有重大调整",false,{"key":16,"text":17,"correct":14},"B","主要施工方法有重大调整",{"key":19,"text":20,"correct":14},"C","主要施工资源配置有重大调整",{"key":22,"text":23,"correct":24},"D","施工企业法人代表变更",true,"项目施工过程中，发生施工企业法人代表变更情况时，施工组织设计不需要进行修改或补充。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]