[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258697":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1258697,842,1,"单选题","在集水井降水法中，集水井应每隔20～40m设置一个，其深度随着挖土深度加深而加深，但要始终低于挖土面（ ）m。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.5～1.0",false,{"key":16,"text":17,"correct":18},"B","0.7～1.0",true,{"key":20,"text":21,"correct":14},"C","0.5～0.7",{"key":23,"text":24,"correct":14},"D","0.7～1.2","在基坑（槽）开挖时，集水井每隔20～40m设置一个，其直径和宽度一般为0.6～0.8m，其深度随着挖土深度加深而加深，要始终低于挖土面0.7～1.0m。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]