[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258685":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1258685,842,1,"单选题","工程项目满足开工条件后，总承包单位应该向监理机构报送的表格是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工现场质量检查记录表",false,{"key":16,"text":17,"correct":14},"B","施工组织设计报审表",{"key":19,"text":20,"correct":21},"C","工程开工报审表",true,{"key":23,"text":24,"correct":14},"D","工程复工报审表","工程项目满足开工条件后，总承包单位应该向监理机构报送的表格是工程开工报审表。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]