[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258682":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1258682,842,1,"单选题","下列文件中，相关单位不需要审批或书面回复的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","监理通知单",false,{"key":16,"text":17,"correct":14},"B","工程暂停令",{"key":19,"text":20,"correct":21},"C","监理联系单",true,{"key":23,"text":24,"correct":14},"D","工程临时延期报审表","下列表式需要审批同意：施工组织设计或施工方案报审表（仅对超过一定规模的危险性较大的分部分项工程专项施工方案）；工程开工报审表；工程复工报审表；施工进度计划报审表；费用索赔报审表；工程暂停令；监理通知单；工程临时或最终延期报审表",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]