[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258672":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1258672,842,1,"单选题","施工现场临时用电设备总容量在50kW及以上者，项目部应编制用电的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工组织设计",true,{"key":16,"text":17,"correct":18},"B","专项方案",false,{"key":20,"text":21,"correct":18},"C","应急预案",{"key":23,"text":24,"correct":18},"D","安全用电措施","施工现场临时用电设备总容量在50kW及以上者，项目部应编制用电的施工组织设计。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]