[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258646":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1258646,842,1,"单选题","在深基坑土方开挖时，应对临时性支护结构进行现场监测，其监测内容不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","支撑结构水平位移",false,{"key":16,"text":17,"correct":14},"B","邻近建筑物沉降",{"key":19,"text":20,"correct":21},"C","挡土结构竖向位移",true,{"key":23,"text":24,"correct":14},"D","挡土结构侧向变形","深基坑土方开挖时，应对临时性支护结构进行现场监测，其监测内容不包括挡土结构竖向位移。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]