[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258601":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1258601,842,1,"单选题","某工程项目桩基工程采用套管成孔灌注桩，为了保证施工质量，桩管灌满混凝土后开始拔管，按照规定，管内应保持不少于（ ）m高的混凝土。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","1.5",{"key":19,"text":20,"correct":21},"C","2",true,{"key":23,"text":24,"correct":14},"D","2.5","按照规定，桩管灌满混凝土后开始拔管，管内应保持不少于2m高的混凝土。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]