[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258598":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1258598,842,1,"单选题","专业工程的暂估价一般应是综合单价，不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工机具使用费",false,{"key":16,"text":17,"correct":14},"B","材料费",{"key":19,"text":20,"correct":21},"C","规费",true,{"key":23,"text":24,"correct":14},"D","人工费","专业工程的暂估价一般应是综合单价，不包括规费。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]