[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258586":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1258586,842,1,"单选题","该工程在第二年1、6月份业主应该支付给承包商的工程款为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","560.00",false,{"key":16,"text":17,"correct":18},"B","986.14",true,{"key":20,"text":21,"correct":14},"C","1009.44",{"key":23,"text":24,"correct":14},"D","171.00","该工程在第二年1、6月份业主应该支付给承包商的工程款为986.14万元。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]