[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258585":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1258585,842,1,"单选题","某建筑工程，合同总价为700万元，工期为5个月，施工单位按照合同约定，按期完成了合同约定的工程项目并一次验收合格，在合同执行期间，按照当地造价管理部门有关规定，整个施工期间建筑材料和设备价差上调10%，根据测算，该工程的建筑材料和设备费占施工产值的比重为60%，工程质量保证金为建筑安装工程造价的3%，竣工验收合格后第三年，该工程发生屋面渗漏，建设单位多次催促施工单位修理，乙方一再拖延，最后建设单位请另一家施工单位修理，修理费5万元。 该工程竣工结算时，施工单位可得到的结算工程款为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","700.00",false,{"key":16,"text":17,"correct":18},"B","719.74",true,{"key":20,"text":21,"correct":14},"C","740.50",{"key":23,"text":24,"correct":14},"D","742.00","该工程竣工结算时，施工单位可得到的结算工程款为719.74万元。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]