[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258582":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1258582,842,1,"单选题","关于横道图施工进度计划的优点，说法正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","能反映各项工作之间关系",false,{"key":16,"text":17,"correct":14},"B","能反映影响工期的关键线路和关键工作",{"key":19,"text":20,"correct":21},"C","直观、方便，应用范围广",true,{"key":23,"text":24,"correct":14},"D","反映工作具有机动时间7","横道图施工进度计划的优点是直观、方便，应用范围广。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]