[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258581":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1258581,842,1,"单选题","当实际施工进度发生拖延时，为加快施工进度而采取的组织措施可以是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","改善劳动条件及外部配合条件",false,{"key":16,"text":17,"correct":14},"B","更换设备，采用更先进的施工机械",{"key":19,"text":20,"correct":21},"C","增加劳动力和施工机械的数量",true,{"key":23,"text":24,"correct":14},"D","改进施工工艺和施工技术","当实际施工进度发生拖延时，为加快施工进度而采取的组织措施可以采取增加劳动力和施工机械的数量。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]