[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258580":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1258580,842,1,"单选题","当双代号网络计划的计算工期等于计划工期时，对关键工作的说法错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","关键工作的自由时差为零",false,{"key":16,"text":17,"correct":14},"B","关键工作的最早完成时间与最迟完成时间相等",{"key":19,"text":20,"correct":21},"C","关键工作的持续时间最长",true,{"key":23,"text":24,"correct":14},"D","关键工作的最早开始时间与最迟开始时间相等","当双代号网络计划的计算工期等于计划工期时，对关键工作的说法错误的是关键工作的持续时间最长。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]