[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258574":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1258574,842,1,"单选题","某建筑公司总承包某电子厂改扩建工程，在施工准备阶段项目经理组织编制了项目总进度计划和项目资源配置计划。结合上述资料，回答下列问题： 总承包单位的施工总进度计划一般由（ ）组织编制。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目经理",false,{"key":16,"text":17,"correct":18},"B","企业技术负责人",true,{"key":20,"text":21,"correct":14},"C","项目技术负责人",{"key":23,"text":24,"correct":14},"D","专业施工员","总承包单位的施工总进度计划一般由企业技术负责人组织编制。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]