[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258571":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1258571,842,1,"单选题","下列不属于施工进度计划检查方法的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","跟踪检查施工实际进度",false,{"key":16,"text":17,"correct":18},"B","因果分析法",true,{"key":20,"text":21,"correct":14},"C","对比分析实际进度与计划进度",{"key":23,"text":24,"correct":14},"D","整理统计检查数据","施工进度计划检查方法包括：跟踪检查施工实际进度、整理统计检查数据、对比分析实际进度与计划进度。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]