[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258569":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1258569,842,1,"单选题","网络图中同时存在”条关键线路，则每条关键线路上各工作过程的持续时间之和（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","都相同",true,{"key":16,"text":17,"correct":18},"B","都不相同",false,{"key":20,"text":21,"correct":18},"C","都有一条最长的",{"key":23,"text":24,"correct":18},"D","都有","网络图中同时存在”条关键线路，则每条关键线路上各工作过程的持续时间之和都相同。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]