[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258566":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1258566,842,1,"单选题","在网络计划的执行过程中检查发现，D工作的总时差由3d变成了1d，则说明d工作的实际进度（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","拖后2d，影响工期2d",false,{"key":16,"text":17,"correct":14},"B","拖后3d，影响工期2d",{"key":19,"text":20,"correct":21},"C","拖后2d，对工期无影响",true,{"key":23,"text":24,"correct":14},"D","拖后3d，对工期无影响","在网络计划的执行过程中检查发现，D工作的总时差由3d变成了拖后2d，对工期无影响",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]