[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258565":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1258565,842,1,"单选题","资源配置计划不包括下列哪一项（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","临时设施计划",true,{"key":16,"text":17,"correct":18},"B","主要材料配置计划",false,{"key":20,"text":21,"correct":18},"C","施工机具配置计划",{"key":23,"text":24,"correct":18},"D","构配件配置计划","资源配置计划包括：劳动力配置计划、主要材料配置计划、施工机具配置计划、构配件配置计划。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]