[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258564":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1258564,842,1,"单选题","某建筑公司总承包某电子厂改扩建工程，在施工准备阶段项目经理组织编制了项目总进度计划和项目资源配置计划。结合上述资料，回答下列问题： 关于工程项目资源特点的说法，错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程所需的资源的种类多、需求量大",false,{"key":16,"text":17,"correct":14},"B","工程项目建设过程的不均衡性",{"key":19,"text":20,"correct":14},"C","资源对项目成本的影响大",{"key":22,"text":23,"correct":24},"D","资源是固定不变的",true,"关于工程项目资源特点的说法，错误的是资源是固定不变的。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]