[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258563":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1258563,842,1,"单选题","下列不属于施工进度计划的调整方法的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","加强安全教育",true,{"key":16,"text":17,"correct":18},"B","增加资源投入",false,{"key":20,"text":21,"correct":18},"C","增减工作范围",{"key":23,"text":24,"correct":18},"D","提高劳动效率","施工进度计划的调整方法包括：增加资源投入、改变某些工作间的逻辑关系、资源供应的调整、增减工作范围、提高劳动效率、将部分任务转移、将一些工作合并。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]