[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258558":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1258558,842,1,"单选题","工程项目资源的特点不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程所需资源的种类多、需求量大",false,{"key":16,"text":17,"correct":18},"B","工程所需资金的数量大",true,{"key":20,"text":21,"correct":14},"C","工程项目建设过程的不均衡性",{"key":23,"text":24,"correct":14},"D","资源对项目成本的影响大","工程项目资源的特点：①工程所需资源的种类多、需求量大；②工程项目建设过程的不均衡性；③资源供应受外界影响大，具有复杂性和不确定性，资源经常需要在多个项目中协调；④资源对项目成本的影响大。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]