[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258555":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1258555,842,1,"单选题","关于后张法预应力（无粘结）钢筋张拉的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预应力混凝土楼盖中的张拉顺序是先张拉楼面梁、后张拉楼板",false,{"key":16,"text":17,"correct":18},"B","板中的无粘结预应力可依次张拉，梁中的无粘结筋可对称张拉",true,{"key":20,"text":21,"correct":14},"C","当曲面无粘结预应力筋长度超过20m时，宜采用两端张拉",{"key":23,"text":24,"correct":14},"D","当长度超过30m时","关于后张法预应力（无粘结）钢筋张拉板中的无粘结预应力可依次张拉，梁中的无粘结筋可对称张拉。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]