[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258549":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1258549,842,1,"单选题","下列施工过程中，不能作为框架结构主体工程施工段划分依据的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","钢筋绑扎",false,{"key":16,"text":17,"correct":18},"B","商品混凝土搅拌",true,{"key":20,"text":21,"correct":14},"C","混凝土浇筑",{"key":23,"text":24,"correct":14},"D","模板安装","框架结构主体工程可行的施工顺序为：绑扎柱钢筋—支柱模板—支梁板模板—绑扎梁板钢筋—浇注柱、梁、板混凝土。现浇钢筋混凝土框架柱施工时；其施工顺序是：柱钢筋绑扎—柱模板安装（包括模板支护）—柱混凝土浇筑—混凝土养护。施工段内每排柱子的浇筑顺序为由外向内对称地顺序浇筑。现浇梁板施工顺序是：铺设梁底模板-梁钢筋绑扎-支梁侧模板并加固^铺设顶板模板^铺设顶板钢筋—浇筑梁板混凝土—混凝土养护。不包括混凝土搅拌",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]