[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258533":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1258533,842,1,"单选题","室内装修工程的施工顺序有整体顺序自上而下和整体顺序自下而上两种，其中整体顺序自上而下的施工优点有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可以与主体结构平行搭接施工",false,{"key":16,"text":17,"correct":18},"B","有利于施工安全",true,{"key":20,"text":21,"correct":14},"C","可以缩短工期",{"key":23,"text":24,"correct":14},"D","工序交叉作业多","室内装修工程的施工顺序有整体顺序自上而下和整体顺序自下而上两种，其中整体顺序自上而下的施工优点有有利于施工安全。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]