[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258529":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1258529,842,1,"单选题","确定施工顺序的基本要求不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","必须符合施工工艺的要求",false,{"key":16,"text":17,"correct":14},"B","必须与施工方法协调一致",{"key":19,"text":20,"correct":14},"C","必须考虑当地的气候条件",{"key":22,"text":23,"correct":24},"D","必须考虑文明施工的要求",true,"确定施工顺序的基本要求：①必须符合施工工艺的要求；②必须与施工方法协调一致；③必须考虑与施工组织的要求；④必须考虑施工质量的要求；⑤必须考虑当地的气候条件；⑥必须考虑安全施工的要求。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]