[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258528":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1258528,842,1,"单选题","钢结构工程一节柱（三层）的竖向焊接顺序是（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","上层梁→中层梁→下层梁→上柱与下柱焊接",false,{"key":16,"text":17,"correct":14},"B","上层梁→中层梁→上柱与下柱焊接→下层梁",{"key":19,"text":20,"correct":21},"C","上层梁→下层梁→中层梁→上柱与下柱焊接",true,{"key":23,"text":24,"correct":14},"D","上层梁→上柱与下柱焊接→中层梁→下层梁","钢结构工程一节柱（三层）的竖向焊接顺序是上层梁→下层梁→中层梁→上柱与下柱焊接",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]