[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258525":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1258525,842,1,"单选题","钢结构工程斜梁的安装顺序是：先从（ ）的两榀钢架开始，刚架安装完毕后将其间的檩条、支撑、隅撑等全部装好，并检查其垂直度。然后以这两榀刚架为起点，向建筑物另一端顺序安装。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","一端的山墙",false,{"key":16,"text":17,"correct":18},"B","靠近山墙的有柱间支撑",true,{"key":20,"text":21,"correct":14},"C","中部",{"key":23,"text":24,"correct":14},"D","中部有柱间支撑力一次施拧","钢结构工程斜梁的安装顺序是：先从靠近山墙的有柱间支撑的两榀钢架开始，刚架安装完毕后将其间的檩条、支撑、隅撑等全部装好，并检查其垂直度。然后以这两榀刚架为起点，向建筑物另一端顺序安装。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]