[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258497":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1258497,842,1,"单选题","关于施工场区平面控制网的布设原则，说法正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","从整体考虑，遵循先局部后整体",false,{"key":16,"text":17,"correct":14},"B","先低精度再高精度",{"key":19,"text":20,"correct":21},"C","选点应选在不受干扰、通视条件良好的地方",true,{"key":23,"text":24,"correct":14},"D","为保证桩位免受损坏，一般采用钢筋插人土体","施工场区平面控制网的布设原则选点应选在不受干扰、通视条件良好的地方",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]