[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258488":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1258488,842,1,"单选题","已浇筑的大体积混凝土基础，其浇筑体表面以内40～100mm位置处的温度与浇筑体表面温度差值不应大于（ ）℃。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","20",false,{"key":16,"text":17,"correct":18},"B","25",true,{"key":20,"text":21,"correct":14},"C","30",{"key":23,"text":24,"correct":14},"D","35","已浇筑的大体积混凝土基础，其浇筑体表面以内40～100mm位置处的温度与浇筑体表面温度差值不应大于25℃。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]