[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1258482":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1258482,842,1,"单选题","砖基础采用台阶式逐级向下放大的做法，一般为每2皮砖挑出（ ）的砌筑方法。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1\u002F2砖长",false,{"key":16,"text":17,"correct":18},"B","1\u002F4砖长",true,{"key":20,"text":21,"correct":14},"C","3\u002F4砖长",{"key":23,"text":24,"correct":14},"D","一皮砖长","砖基础采用台阶式逐级向下放大的做法，一般为每2皮砖挑出1\u002F4砖长的砌筑方法。",{"id":6,"name":27,"category":28,"favorite":29},"(土建施工)专业管理实务 岗位知识","建筑工程",0]